The below listed documents may not be readable via Optical Character Recognition. To receive public notices via email for the Huntington District Regulatory Division please send an email to LRH.Permits@usace.army.mil indicating that you would like to be placed on the public notice electronic distribution list. Your email should include which state(s) Ohio and/or West Virginia in which you would like to receive public notices.

LRH 2016-00006-OH

Published March 22, 2017
Expiration date: 3/18/2022

          

CORPS OF ENGINEERS REGULATORY PROGRAM

REISSUANCE AND ISSUANCE OF NATIONWIDE PERMITS 

WITH OHIO ENVIRONMENTAL PROTECTION AGENCY

 401 WATER QUALITY CERTIFICATION

and

OHIO DEPARTMENT OF NATURAL RESOURCES CONSISTENCY DETERMINATION UNDER THE COASTAL ZONE MANAGEMENT ACT

 

 

    On January 6, 2017, the U.S. Army Corps of Engineers (Corps) published in the Federal Register (82 FR 1860) the final rule for the administration of its nationwide permit (NWP) program regulations under the Rivers and Harbors Act of 1899, Section 404 of the Clean Water Act, and the Marine Protection, Research and Sanctuaries Act.  The rule became effective on March 19, 2017.  These NWPs will expire on March 18, 2022.

 

            An integral part of the Corps’ regulatory program is the concept of NWPs for minor activities.  NWPs are activity specific and are designed to relieve some of the administrative burdens associated with permit processing for both the applicant and the Federal government.  The NWPs are issued by the Chief of Engineers and are intended to apply throughout the entire U.S. and its territories.  The Corps Districts representing Ohio have imposed regional conditions on the NWPs that are applicable throughout the entire state.  For convenience, all NWPs with the appropriate regional, general, and special conditions are attached.

 

            The NWPs are not valid until the appropriate state agency certifies the discharge does not violate state water quality standards.  The Ohio Environmental Protection Agency (OEPA) granted water quality certification and imposed general conditions on NWP 19, and specific conditions on NWP nos. 3, 4, 5, 6, 7, 12, 13, 14, 15, 16, 18, 20, 22, 23, 25, 27, 29, 30, 31, 32, 33, 34, 35, 36, 37, 38, 39, 40, 41, 42, 43, 45, 49, 51, and 53.

 

            The OEPA denied water quality certification for NWP 17-Hydropower Projects, NWP 21- Surface Coal Mining Activities, NWP 44-Mining Activities, NWP 46-Discharges in Ditches (revoked for use in Ohio), NWP 48-Commercial Shellfish Aquaculture Activities, NWP 50-Underground Coal Mining Activities, and NWP 52-Water-Based Renewable Energy Generation Pilot Projects (revoked for use in Ohio).  Discharges that are NOT included in OEPA’s certification of the NWPs must obtain either individual water quality certification or a waiver from:

 

            Ohio Environmental Protection Agency

            Division of Surface Water                                                         

            PO Box 1049

            Columbus, Ohio 43216-1049

            (614) 644-2001

 

            In addition, any state with a federally-approved Coastal Zone Management Act (CZMA) plan must agree with the Corps determination that the activities authorized by NWPs which are within, or will affect any land or water uses or natural resources of the state’s coastal zone, are consistent with the CZMA plan.  The Ohio Department of Natural Resources (ODNR) concurred with the Corps Federal Consistency Determination on NWPs nos. 1, 2, 4, 5, 6, 8, 9, 10, 11, 16, 19, 20, 21, 22, 23, 24, 25, 27, 28, 29, 30, 31, 32, 33, 34, 35, 37, 39, 40, 41, 42, 43, 45, 48, 49, 50, 51, and 53, and imposed specific conditions on NWP nos. 3, 7, 12, 13, 14, 15, 17, 18, 36, and 54.  Activities which are NOT included in ODNR’s concurrence of the NWPs must obtain a project specific CZMA consistency determination from:

  

            Ohio Department of Natural Resources

            Office of Coastal Management

            105 West Shoreline Drive

            Sandusky, Ohio 44870

            (419) 626-7980

 

            Some NWP activities may proceed without notifying the Corps, as long as those activities comply with all applicable terms and conditions of the NWPs, including regional conditions imposed by division engineers.  A non-reporting NWP may become a reporting NWP (requires the submittal of a Pre-Construction Notification [PCN] to the Corps in accordance with NWP General Condition 32 and Regional General Condition 6) if the activity has the potential to affect a historic property (See NWP General Condition 20), federally-listed endangered or threatened species or their habitat (See NWP General Condition 18), waters of special concern (Regional General Condition 5), National Wild and Scenic Rivers (See NWP General Condition 16 and Regional General Condition 6(d)) or waters listed in Regional General Condition 4 during the in-water restriction periods established by the ODNR.  Applicants must review the water quality certification general and NWP-specific terms and conditions and submit an application to the OEPA, at the address provided above, when an individual 401 Water Quality Certification is required. 

  

Many of the proposed NWPs require advance notification (PCN) to the district engineer before commencing those activities, to ensure that the activities authorized by those NWPs cause no more than minimal individual and cumulative adverse environmental effects.  The notification must be made in writing as early as possible prior to commencing the proposed activity.  The notification procedures are located under NWP General Condition 32 and Regional General Condition 6.  The notification to the Corps can be made concurrently with the request for individual state water quality certification, if required.  The district engineer may require an individual permit for any activity determined to have more than minimal adverse environmental effects, individually or cumulatively, on the aquatic environment or would be contrary to the public interest.

 

            The NWPs provide a simplified, expeditious means of project authorization under the various authorities of the Corps.  We encourage prospective permit applicants to consider the advantages of NWP authorization during the preliminary design of their projects.  Assistance and further information regarding all aspects of the Corps regulatory program may be obtained by contacting:

 

 

BUFFALO DISTRICT

Address:          U.S. Army Corps of Engineers, Buffalo District

                        1776 Niagara Street

                        Buffalo, New York 14207-3199 

Phone:             (716) 879-4330

 

HUNTINGTON DISTRICT

Address:          U.S. Army Corps of Engineers, Huntington District

                        502 Eighth Street

                        Huntington, West Virginia  25701-2070

Phone:             (304) 399-5210

 

LOUISVILLE DISTRICT

Address:          U.S. Army Corps of Engineers, Louisville District

                        Post Office Box 59

                        Louisville, Kentucky  40201-0059

Phone:             (502) 315-6733

 

PITTSBURGH DISTRICT

Address:          U.S. Army Corps of Engineers, Pittsburgh District

                        William S. Moorhead Federal Building

                        1000 Liberty Avenue

                        Pittsburgh, Pennsylvania  15222-4186

Phone:             (412) 395-7155