Construction of the Bolivar Dam seepage barrier
remains ahead of schedule, it is currently 90 percent complete. Members of the
Huntington District staff had the rare opportunity to visually view a section
of the seepage barrier when it was excavated to allow the construction of an
adjacent panel at a lower elevation. The visual inspection confirmed that the
construction methods are producing a high quality seepage barrier with uniform
wall thickness and geometry.